Preparation foundation: Clean up debris, grave on the site to ensure that the foundation is flat, and carry out the necessary filling and compaction.

Laying the bottom layer: lay a layer of concrete or asphalt, usually 5-10 cm thick.

Mixthe material in proportion: MixSSG sports’acrylic pigments, adhesive 108, cement, sand and water in proportion to make a uniformresurfacer.


















Spray primer: Apply a layer of primer on the surface of the underlying concrete or asphalt




Apply theاكريليك resurfacer:Apply the mixed acrylic paint evenly on the surface of the primer,use professional tools to flatten and compact the coating surface
Secondaryscraping: After the first layer of paint is dried, apply the same layer of acrylic paint to improve durability and aesthetics.




Applytop coat :Scrape Acrylic Surface Color Layer معinner and outer court separated



Linemaking: draw the line after the surface dried.


Completed: After the surface وline is fully dried and the necessary cleaning work is carried out, the construction of the hard acrylic floor of the tennis court is completed.
Notes:
 
1. Construction should avoid severe weather conditions such as high temperature and strong wind.
2.Before construction, the quality and storage time of the coating should be checked, and the products that meet the standards should be selected.
3.Before construction, you should carefully read the product manual and operating specifications to ensure that the construction follows the correct steps.